Prague Logistics Hub is a K2 Engineering project that started in January 2026. Phase 1 (site systems and inbound automation) was handed over in June 2026; phase 2 (outbound and reporting) is in progress.
Open items from the handover note: the reporting layer is waiting on K2's data warehouse access, and change request CR-03 for a second loading-dock scanner is still unsigned.
Petr Dvořák is the project manager and Martin Král owns the integration design. The last client steering meeting was on 20 August 2026.
Sources
Preview · Shared drive
Objective: site systems for a new logistics hub. Phase 1 inbound automation (Q1–Q2 2026), phase 2 outbound and reporting (Q3 2026).
Preview · SharePoint
Open items: (1) reporting layer awaiting K2 data warehouse access; (2) change request CR-03 second dock scanner — unsigned.
Preview · Teams
Phase 2 on track for outbound; reporting slipping pending DWH access. K2 to confirm CR-03 by end of month.